INVITATION TO BID

 

INTRODUCTION
Mark Wilson Construction (MWC) is inviting suppliers and subcontractors to submit bid proposals for the Tranquillity H.S. Aquatic Center Project. The project is located at 6052 Juanche Street, Tranquillity, CA  93668.

 

DESCRIPTION OF WORK
Increment 1:
  This project consists of the new construction of a new pool equipment building, modernization of dive pool (DSA A#33437) conversion into a lean to swim pool, new 10-lane modular swimming pool, new fabric shade structure, new PC approved scoreboard, new waterslide, new splash pad area, landscaping, and concrete pool deck, and new utilities, and associated site access.

 

 

DURATION OF WORK

Time to Complete:  319 Calendar Days

Wage Scale:  Prevailing Wage

Delivery Method:  GC Hard Bid

Liquidated Damages:  $500/day

Minority Goals:  None

DIR Register:  Yes